We advise clients on a broad range of construction disputes including dispute board proceedings, intermediate and alternative dispute resolution, contract administration, and management of claims arising during the course of a project, as well as arbitrations and litigations.
We advise clients on a broad range of construction disputes including dispute board proceedings, intermediate and alternative dispute resolution, contract administration, and management of claims arising during the course of a project, as well as arbitrations and litigations.
Thermal Power Plant
India, South Korea and Singapore
SIAC Rules, Singapore seated, Indian law
India, South Korea and Singapore
Representing two Indian companies in a shareholder dispute against a South Korean sovereign company in a thermal power plant construction project in Maharashtra.
Lost Profits
Early Dismissal Application
Duty of Good Faith
Limitation
Conflict of Laws
Biofuel plant
India, Philippines, Australia
SIAC Rules, Singapore seated, English law
India, Philippines, Australia
Representing an Indian company in a tri-partite arbitration under an EPC contract for construction of a biofuel plant in the Philippines; against an Australian employer and a Filipino co-contractor.
Delay
Latent Defects
Prolongation
Quantum Meruit
Contract Validity
Drilling Rig Conversion
India, Singapore and Abu Dhabi
SIAC Rules, Singapore seated, Singapore law
India, Singapore and Abu Dhabi
Representing a Singaporean and an Indian company in an arbitration concerning breach of a consortium agreement for a rig conversion project against an Abu Dhabi shipyard.
Anti-suit Injunction
Repudiatory Breach
Tortious Interference
URDG 758
CFBC Boiler
Turkey and India
ICC Rules, Turkey seated, Turkish law
Turkey and India
Advising an Indian company for its dispute against the Turkish employer relating to the construction of a circulating fluidized bed combustion boiler in Istanbul, Turkey.
Wrongful Termination
Minimum Performance
Prolongation
Defective Test Runs
Highway Construction
Turkey and Kazakhstan
SIAC Rules, Singapore seated, Kazakh law
Turkey and Kazakhstan
Advising a Turkish company in an arbitration concerning termination of a contract for renovation of highways in Kazakhstan against a Kazakh state-owned enterprise.
FIDIC Contract
Emergency Arbitration
Wrongful Invocation of Bank Guarantee
Conversion from MODU to MOPU
India and Singapore
Ad-hoc international arbitration; India seated; Indian law
India and Singapore
Representing a Singaporean and an Indian company in their dispute under an EPC contract in for conversion of a mobile offshore drilling unit to a mobile offshore production unit, against an Indian state-owned enterprise.
Disruption
Extension of Time
Prolongation
Variations
Market Intelligence
Acceleration Costs
Drilling Rig Conversion
India
India seated, Indian law
India
Representing an Indian company in its dispute against its project manager under a profit-sharing project management agreement.
Limitation
Agreement to Agree
Restitution
Efflux of Time
Parole Evidence
LPG Storage Vessels
India
India seated, Indian law
India seated, Indian law
Advising an Indian company in its ad-hoc arbitrations concerning termination of its contracts for construction of 3x300 MT mounted storage vessels, against an Indian state-owned enterprise.
Wrongful Termination
Liquidated Damages
Arbitrator’s Conflict of Interest
Delays
Oil Tankage Platforms
India
India seated, Indian law .
India
Advising an Indian company in its dispute against an Indian state-owned enterprise under an EPC contract for oil tankage platform in Gujarat.
Wrongful Termination
Liquidated Damages
Arbitrator’s Conflict of Interest
Delays
Civil Construction
India
India seated, Indian law
India
Advising an Indian company in its dispute against an Indian state-owned oil & gas entity under an EPC contract for civil construction in Lucknow.
Arbitration Agreement Validity
Court’s Assistance in Appointment of Arbitrator